Zekon / Case study
Case study

Crane beams Austria

Place of realization

Austria

Duration of the project

start of March 2023 – end of deliveries September 2023

Type of the order

prefabrication and delivery of crane beams

Quantity of steel used

800 tons

An order from the Client from Austria for the prefabrication and delivery of over 800 Mg of crane beams.

The order concerned elements with lengths of up to 21.5m and individual element weights exceeding 16Mg. The beams will be installed in the steel mill’s rolling mill hall, where work takes place 24 hours a day, 7 days a week. These elements will be subjected to constant dynamic loads.

In order to extend the life of the beams, the Client requires that quality requirements exceed the standards, especially in relation to the dimensional tolerances of the beams and the scope of weld testing, which Zekon has coped with very well.